Where trees are to be retained on a development site, the conditions of consent often require a project arborist to oversee their protection from demolition through to completion. Sydney Arborist acts as project arborist for builders, developers, architects and homeowners, making sure retained trees are protected as approved and that the certification council needs is in place.

What a project arborist does

  • Inspects and certifies tree protection, such as fencing, trunk protection and ground protection, before demolition or construction starts
  • Attends the hold points set out in the Tree Protection Plan and Specification
  • Supervises work inside the Notional Root Zone (NRZ), such as excavation, footings and services, so it is carried out with root-sensitive methods
  • Advises on roots and branches affected by the works, and on any pruning that has been approved
  • Records each site visit with photos and a written report for the builder, certifier and council
  • Provides final certification that the trees were protected as required, ready for the occupation certificate

Tree protection on site

Examples of tree protection installed on recent projects and checked by the project arborist.

Timber trunk protection and no-access sign on a retained tree

Trunk protection with timber battens and a no-access sign

Timber trunk protection on a Norfolk Island pine at a construction site

Trunk protection on a Norfolk Island pine beside a construction site

Tree protection fencing and no-access signs around retained trees in a garden

Tree protection fencing and signage around a garden zone

Tree protection fencing with shade cloth around a retained eucalypt

Tree protection fencing with shade cloth around a large eucalypt

Site supervision

Where works come close to retained trees, the project arborist attends so roots can be assessed as they are exposed, and decisions made on site.

Retained eucalypt standing beside a bulk excavation

A retained eucalypt beside bulk excavation

Excavation supervised by the project arborist beside retained palms

Supervised excavation beside retained palms

Typical hold points

The exact hold points are set by the conditions of consent and the Tree Protection Specification for each project. They commonly include:

  • before demolition or site establishment, once tree protection is installed
  • during excavation or other approved work inside a Notional Root Zone
  • whenever tree protection needs to be moved or changed
  • at completion, before the occupation certificate

Each inspection is recorded, so there is a clear trail showing the trees were looked after throughout the job.

Frequently asked questions

Do I need a project arborist?

Check your conditions of consent. If they request a project arborist, or require tree protection to be inspected or certified, you will need one. Councils commonly ask for an AQF Level 5 arborist for this role.

When should I engage a project arborist?

Before demolition or any site work starts, so the tree protection can be inspected and certified at the first hold point.

Can the tree protection fencing be moved?

Only with the project arborist’s approval. Any change is assessed and recorded, and the protection is re-inspected.

Need a project arborist? Call Sydney Arborist on 0423 568 159 or send your conditions of consent.